KNAUF INSULATION S.R.O., NOVÁ BAŇA – 1ST STAGE OF +130 M REINFORCED CONCRETE CHIMNEY RECONSTRUCTION
In December 2016 we have successfully completed a first stage of a 130 m high reinforced concrete monolithic chimney reconstruction in KNAUF Insulation, s.r.o., Nová Baňa. The project was delivered in advance compared to original plan.List of works carried out in the first stage:
- Reconstruction of the chimney upper part from +130 m to +126 m;
- Reinforcement of the chimney upper part by a system of MONOSTRAND supporting pre-stress elements;
- Removing the original confusor and installing a new load-bearing grate of the liner including a new confusor and chimney cap using a helicopter;
- Removing parts of inner lining according to static plan and rehabilitation of the remaining inner lining;